Website development timeline template
Last updated
A website development timeline template is a plan that puts each phase of a build in order, with a start date, an end date and an owner for each. It also marks every point where work waits on the client. It holds no fixed lengths: you set the dates for each project from its scope and the client's own calendar.
What goes in a website development timeline template?
It holds the phases in order, the owner of each, what each phase depends on and the points where you wait on the client. Add a start date and an end date column, and fill them in for each project.
| Phase | Owner | Can't start until | Waits on the client for |
|---|---|---|---|
| Kickoff | Project lead | The proposal is signed | The kickoff call |
| Discovery | Project lead | Kickoff is done | Answers to your questions |
| Content | Writer or client | The page list is approved | The copy and images |
| Design | Designer | Discovery is done | Approval of the design |
| Build | Developer | The design is approved | Nothing |
| Quality checks | Tester | The build is done | Nothing |
| Client review | Project lead | The checks are done | The change list and sign-off |
| Launch | Developer | The client signs off | Access to the domain |
Each phase also has tasks to tick off. For the tick list for each phase, see the website project management checklist.
How do you set a project timeline for website development?
Work backward from the launch date the client wants, and set each phase's dates with the people who'll do the work. Then mark each client waiting point and put a due date on it.
- Ask the client for their launch date, and what it's tied to.
- List the phases in order, and note which ones can't start until another ends.
- Ask each owner how long their phase takes on this scope, and turn the answer into dates.
- Mark each client waiting point, with the date you need their reply.
- Leave some slack before launch for the last round of changes.
- Send the timeline to the client and get their yes on the waiting points.
- Update it each week, and tell the client when a date moves and why.
Late feedback pushes back every date after it. Say so in writing at kickoff, so a slow reply doesn't turn into a surprise on launch day.
The order of the phases comes from how the build runs. For the production stages, see the website development process.
The Ultimate Task Delegation Template from DeskTeam360 is free. Use it to hand off tasks, website builds included, once you've given your email.
Can you build the timeline in Excel?
Yes, any spreadsheet can hold a build timeline, Excel included. A few columns and some shaded cells are enough.
- Make one row for each phase, with columns for the owner, the start date, the end date, the client waiting point and the status.
- Add a column for each week of the project across the top.
- Shade the cells between each phase's start and end dates, so the sheet reads like a bar chart. This layout is known as a Gantt chart.
- Give the client waiting points their own color.
- Save a blank copy as your template, and copy it for each new build.
Before you share it, check that every date has an owner and every waiting point has a due date.
Hand off your next build task in writing with DeskTeam360's Ultimate Task Delegation Template. It's free, it names website builds among the tasks it fits, and it asks only for your email.
More on Planning the build
- The web design process, stage by stage
- The website development process, from plan to launch
- Web design process template: the stages an agency repeats
- All guides
Sources
- DeskTeam360's page for the Ultimate Task Delegation Template, start.deskteam360.com/ultimate-task-delegation-template
- DeskTeam360's About page, deskteam360.com/about
What changed
- : Page first published.